Check out the galleries below to see our current construction progress, which we will be updating monthly.
Please follow our Facebook page to get the latest construction updates and check out Instagram for the latest photos.
The weather hasn't slowed down the construction of our beautiful resort. We are currently building 13 new homes, with the next 4 residents moving in by the end of April.
The indoor pool and outdoor pools have both started construction. All other amenities are progressing nicely.
Stayed tuned for more updates on our Facebook and Instagram pages.
We are pleased to announce our first five residents are now occupying their beautiful homes. The next five homes are currently being constructed which includes some stock homes.
Civils are progressing nicely which are leading to our amenities section of the resort. The amenities will start construction and will be completed in 6 months time, excluding the clubhouse, men's shed and caravan parking.